Tribe served as Lead and Financial Advisor to Dubai Municipality for the Dubai Waste Management Centre – Advisor to Dubai Municipality on the procurement of the first project financed waste to energy project in the GCC.

The Dubai Waste Management Centre ("DWMC") is the GCC region’s first project-financed waste-to-energy facility, structured as a Public-Private Partnership (PPP). Designed to handle 1.9 million tonnes of municipal solid waste annually, the 200 MW facility is one of the largest of its kind globally.

TRIBE ADVISORY'S ROLE

The Dubai Waste Management Centre Project (“DWMC”) was procured as a design, build, finance, operate and maintain PPP project for a 1.9 million tonne per annum (200 MW) municipal solid waste to energy facility. 


The project is being co-developed by a consortium comprising Dubal Holding, ITOCHU Corporation, Hitachi Zosen Inova, BESIX Group, and Tech Group, as the project developers and joint venture partners in the project company. They appointed Besix and HZI to build the facility and provide the long-term operations and maintenance of the facility.

Background hi-res.png

Tribe logo white

© Tribe Infrastructure Group.

Tribe Infrastructure Limited is regulated by the ADGM Financial Services Regulatory Authority. For further information please refer to 'Terms & Conditions. 

Social

  • LinkedIn
bottom of page